2015.0 In-Depth Release Schedule

2015.0 Schedule (as of 26 Nov 2013)
Deadline (from 22 Nov 2013) Task
+1 week Cooker is now pointing to 2015.0
Toolchain updates(gcc, glibc, perl, etc)
Mass Rebuild
+4 months Free-standing changes & Feature Proposals created/implemented
Feature window closes 2 weeks before this ends.
+1 month Free-standing changes completed and features proposals are at least 50%.
2013.1 ISO respin
+1 week MINOR FREEZE
Software String Freeze
+2 weeks ALPHA 1
+2 weeks MAJOR VERSION FREEZE
Items such as major desktop environments should not be changing much.
+2 weeks ALPHA 2
+1 week ALL CHANGES MUST BE COMPLETE BY NOW
FEATURE FREEZE
Cooker branches and points to 2016.0 for toolchain updates and eventual mass rebuild.
+2 weeks BETA
+1 week MINOR VERSION FREEZE
Translation Freeze
+3 weeks RC
+2 weeks GA